How to create and organize tasks and subtasks in Microsoft Project

Tested on: Microsoft Project Professional 2024 for Windows and current Project for the web guidance, October 2026.

Microsoft Project works best when you separate two ideas: the task list describes the work, while the outline shows how that work belongs together. A row at the top level can stand alone or act as a summary task. Indented rows beneath it are subtasks. This structure lets you plan by phase without losing the detailed actions people must complete.

This guide explains how to create tasks and subtasks on Microsoft Project, mainly in the Windows desktop app. It also shows the equivalent web workflow because Microsoft is moving Project for the web capabilities into the new Planner experience. The most important rule is consistent across both versions: hierarchy organizes work, but it does not create dependencies between tasks.

Choose the Project experience you are using

Microsoft currently has more than one task-planning surface, and the commands are not identical. Confirm your screen before following a menu path.

Project desktop

Project Professional and Project Standard use a spreadsheet-like task table beside the Gantt chart. You create a hierarchy by selecting a task row and using Task > Indent Task. The row immediately above becomes the summary task, and the indented row becomes its subtask.

The desktop app is the focus of the steps below. It provides scheduling controls such as predecessors, constraints, calendars, resource assignments, baselines, and critical-path analysis.

Project for the web and the new Planner

In the web experience, add rows in Grid view, open the three-dot menu beside a task, and choose Make subtask. Use Promote subtask to move the row back up. Microsoft is folding Project for the web into Planner, so your tenant may already show Planner branding or slightly different navigation.

If you only need a team board with lightweight work breakdown, a lighter-weight way to structure shared work may be easier than a full desktop schedule. Choose Project desktop when dates, dependencies, calendars, and resource loading need tighter control.

Build the task list before creating the hierarchy

Start in Gantt Chart view and enter the work in the Task Name column. You can type directly into blank rows, paste a list from Excel, or insert a new task between existing rows. Use short, action-oriented names that describe an outcome, such as “Approve design” or “Configure test environment.”

For a top-down plan, enter the main phases first and put their detailed activities below them. For a bottom-up plan, list all known activities, then add phase rows above the groups. Either method works, but avoid mixing phase names and individual actions at the same outline level without a clear reason.

Add these fields before or shortly after you organize the outline:

  • Duration: the expected working time for each actionable task.
  • Start and Finish: calculated by Project for automatically scheduled tasks, or entered manually when appropriate.
  • Predecessors: the task relationships that control sequence.
  • Resource Names: the people or resources responsible for the work.

Do not spend time perfecting every date before the outline is stable. Moving a summary task also moves its subtasks, and reorganizing rows later can make a carefully formatted early schedule harder to review.

Turn task rows into summary tasks and subtasks

The simplest pattern is one phase row followed by the activities that belong to that phase. For example, enter “Planning” in one row, then add “Confirm scope,” “Identify stakeholders,” and “Approve schedule” below it.

Indent tasks in Project desktop

  1. Select the full row for the task you want to place under the row above.
  2. Open the Task tab on the ribbon.
  3. In the Schedule group, select Indent Task.
  4. Repeat for the other rows that belong to the same phase.

You can select several adjacent task rows and indent them together. Project changes the row above into a summary task and displays its children beneath it. To undo the relationship, select the subtask and choose Outdent Task. The keyboard shortcuts Alt+Shift+Right Arrow and Alt+Shift+Left Arrow also indent and outdent selected tasks in Project desktop.

Create deeper outline levels carefully

A subtask can also become a summary task for another level. For example, “Build solution” could contain “Configure environment,” which then contains “Create access groups” and “Apply policies.” Use deeper levels only when they clarify ownership or reporting. A schedule with many nested levels becomes difficult to scan and maintain.

Microsoft recommends assigning resources to the actionable subtasks rather than to summary tasks. A summary row represents combined work, so assigning a person to both the parent and every child can double-count work or make overallocations harder to resolve.

Microsoft Project task and subtask outline workflow
Add the phase and task rows first, then indent the detailed work and review the resulting Gantt outline.

Make subtasks in the web experience

In Project for the web or a premium Planner plan, open Grid view and create the parent and child rows. Select the three-dot menu beside a child row, then choose Make subtask. To move it out of the group, use Promote subtask. If that command is missing, check the plan type and confirm that you are in a view that supports task hierarchy.

Add schedule logic after the outline is correct

Indenting a task does not mean it must start after the previous task finishes. The outline describes membership; links describe sequence. Select tasks that must run in order and use Link Tasks, or enter predecessor IDs in the Predecessors column. Then review the Gantt bars to confirm that the calculated dates match the intended flow.

Enter durations and assignments on the subtasks that represent real work. Summary dates normally reflect their children, but summary values do not all behave the same way. Cost and work can roll up from subtasks, while duration reflects the span between the earliest start and latest finish rather than a simple total.

After the schedule is usable, your team may need a shared collaboration layer around the plan for conversations, files, and routine updates. Keep Microsoft Project as the scheduling source of truth if people are also discussing the work in Teams.

Check the outline and correct common mistakes

Use the expand or collapse control beside a summary task to show or hide only that branch. To inspect the entire plan by level, open View > Outline and select an outline level or All Subtasks. This is a quick way to check whether activities sit under the right phase.

Watch for these common problems:

  • The wrong parent appears. A subtask always belongs to the nearest non-indented task above it. Outdent the row, move it below the intended parent, and indent it again.
  • Dates do not follow the outline. Add or correct predecessor links; hierarchy alone does not establish scheduling order.
  • A summary row is overloaded. Put durations, assignments, and progress on the actionable subtasks unless there is a deliberate planning reason not to.
  • Deleting a phase removes too much. Moving or deleting a summary task affects its subtasks. Outdent any rows you want to keep before deleting the parent.
  • The plan is difficult to read. Reduce unnecessary nesting and use outline levels to show only the detail needed for the current review.

Questions about Microsoft Project task hierarchy

What is the difference between a summary task and a subtask?

A summary task groups the indented rows beneath it and displays combined schedule information. A subtask is one of those detailed rows. The relationship is created by outline level, not by task name or by a predecessor link.

Does indenting a task create a dependency?

No. Indenting creates a parent-child structure, while dependencies determine timing between tasks. Use links or the Predecessors field when one task must control the start or finish of another.

Can I assign a person to a summary task?

Project allows assignments in several situations, but Microsoft advises assigning resources to the subtasks that contain the actual work. Assigning the same resource to a summary task and its children can distort workload calculations and complicate over-allocation troubleshooting.

Why can’t I find Make subtask in the browser?

The browser command depends on the plan type and supported view. Confirm that the plan includes premium hierarchy features and switch to Grid view. Your organization may also show the new Planner interface because Microsoft is transitioning Project for the web capabilities there.

Put the hierarchy to work

Build the outline around real deliverables: phase rows at the higher level and actionable work beneath them. Once the parent-child structure reads clearly, add links, durations, and assignments so Project can calculate a useful schedule. Keep the hierarchy shallow enough for the team to understand, and use outline levels during reviews so each audience sees the right amount of detail. That order—list, organize, then schedule—usually produces a cleaner plan than entering dates before the work breakdown is settled.